Action Date | Action Description |
---|---|
Executive Sign Off | |
Sent to Photo Copy | |
Assent Requirement | |
Jan 08, 2024 | Assent Application Received |
Jan 11, 2024 | Administrative Review for Completeness |
Jan 17, 2024 | Bio Team Review for Completeness |
Jan 17, 2024 | Application Accepted |
Jan 17, 2024 | Project Manager |
Feb 15, 2024 | Additional Information Requested from Applicant |
Feb 26, 2024 | HPHC Historical Preservation No Effect |
Mar 31, 2025 | Plans Received |
Apr 30, 2025 | Biologist Report |
May 02, 2025 | Typist for Processing |