Action Date | Action Description |
---|---|
Land Evidence Date | |
Mar 06, 2025 | Freshwater Wetlands Application - New - received |
Mar 12, 2025 | Administrative Review for Completeness |
Mar 18, 2025 | Eng Team Review for Completeness |
Mar 18, 2025 | Bio Team Review for Completeness |
Mar 18, 2025 | Project Manager |
Mar 18, 2025 | Application Accepted |
Apr 22, 2025 | HPHC Historical Preservation No Effect |
May 12, 2025 | Biologist Report |
May 12, 2025 | Engineering Report |
May 15, 2025 | Typist for Processing |
May 15, 2025 | Executive Sign Off |
May 15, 2025 | Sent to Photo Copy |
May 15, 2025 | Permit Approved |
May 16, 2025 | Permit Mailed |