Action Date | Action Description |
---|---|
Ready to Schedule Semi-Monthly Meeting | |
Feb 19, 2025 | Assent Application Received |
Feb 24, 2025 | Administrative Review for Completeness |
Mar 11, 2025 | Eng Team Review for Completeness |
Mar 11, 2025 | Project Manager |
Mar 11, 2025 | Application Accepted |
Mar 11, 2025 | Category B assigned |
Apr 10, 2025 | HPHC Historical Preservation No Effect |
Apr 14, 2025 | 30 day Public Notice Issued |
May 14, 2025 | Public Notice End Date |
Jun 03, 2025 | Additional Information Received |
Jun 03, 2025 | Supervisor Biologist SignOff |
Jun 03, 2025 | Supervisor Engineer SignOff |
Jun 03, 2025 | Engineering Report |
Jun 04, 2025 | Executive Signoff of Staff Reports |