Action Date | Action Description |
---|---|
US Army Corps of Engineers Approval Required | |
Land Evidence Date | |
Dock Post-Construction Certification by Engineer received. | |
Aug 14, 2024 | Assent Application Received |
Aug 15, 2024 | Administrative Review for Completeness |
Aug 15, 2024 | Comments Received |
Sep 04, 2024 | Eng Team Review for Completeness |
Sep 04, 2024 | Application Accepted |
Sep 04, 2024 | Project Manager |
Sep 12, 2024 | 30 day Public Notice Issued |
Sep 13, 2024 | HPHC Historical Preservation No Effect |
Oct 12, 2024 | Public Notice End Date |
May 09, 2025 | Engineering Report |
May 14, 2025 | Typist for Processing |
Jun 09, 2025 | Executive Sign Off |
Jun 09, 2025 | Sent to Photo Copy |
Jun 09, 2025 | Permit Approved |
Jun 10, 2025 | Permit Mailed |