Action Date | Action Description |
---|---|
Land Evidence Date | |
Aug 26, 2024 | Assent Application Received |
Aug 30, 2024 | Administrative Review for Completeness |
Sep 10, 2024 | Bio Team Review for Completeness |
Sep 10, 2024 | Deficient Application - Owner Notification Sent |
Nov 06, 2024 | Deficiency Response Received |
Nov 15, 2024 | Bio Team Review for Completeness |
Nov 15, 2024 | Application Accepted |
Nov 15, 2024 | Project Manager |
Dec 09, 2024 | HPHC Historical Preservation No Effect |
Jun 03, 2025 | Biologist Report |
Jun 09, 2025 | Typist for Processing |
Jun 09, 2025 | Executive Sign Off |
Jun 09, 2025 | Sent to Photo Copy |
Jun 09, 2025 | Permit Approved |
Jun 10, 2025 | Permit Mailed |