Action Date | Action Description |
---|---|
HPHC Review Pending | |
Enforcement Compliance Inspection Required | |
Apr 27, 2022 | Assent Application Received |
Apr 27, 2022 | Administrative Review for Completeness |
Apr 27, 2022 | CHA Worksheet received |
May 05, 2022 | Bio Team Review for Completeness |
May 05, 2022 | Application Accepted |
May 05, 2022 | Project Manager |
May 25, 2022 | HPHC Historical Preservation No Effect |
May 25, 2022 | HPHC Review Pending |
Jun 29, 2022 | Biologist Report |
Jul 07, 2022 | Typist for Processing |
Jul 07, 2022 | Executive Sign Off |
Jul 07, 2022 | Sent to Photo Copy |
Jul 07, 2022 | Permit Approved |
Jul 07, 2022 | Permit Mailed |
Jul 15, 2022 | Land Evidence Date |
Jun 04, 2025 | Modification Request |
Jun 04, 2025 | Extension of Permit Request |
Jun 09, 2025 | Administrative Review for Completeness |
Jun 11, 2025 | Application Accepted |
Jun 11, 2025 | Bio Team Review for Completeness |
Jun 11, 2025 | Project Manager |
Jun 12, 2025 | Biologist Report |