Action Date | Action Description |
---|---|
Permit Mailed | |
Feb 06, 2025 | Freshwater Wetlands Application - New - received |
Feb 13, 2025 | Administrative Review for Completeness |
Feb 25, 2025 | Eng Team Review for Completeness |
Feb 25, 2025 | Bio Team Review for Completeness |
Feb 25, 2025 | Project Manager |
Feb 25, 2025 | Application Accepted |
May 07, 2025 | Biologist Report |
May 07, 2025 | Engineering Report |
Jul 02, 2025 | HPHC Historical Preservation No Effect |
Jul 03, 2025 | Executive Sign Off |
Jul 03, 2025 | Sent to Photo Copy |
Jul 03, 2025 | Permit Approved |
Jul 03, 2025 | Typist for Processing |