Action Date | Action Description |
---|---|
Land Evidence Date | |
Jan 14, 2025 | Assent Application Received |
Feb 13, 2025 | Administrative Review for Completeness |
Feb 13, 2025 | Bio Team Review for Completeness |
Feb 18, 2025 | Deficient Application - Owner Notification Sent |
Feb 28, 2025 | Deficient Application Picked Up |
May 29, 2025 | Deficiency Response Received |
Jun 06, 2025 | Additional Information Received |
Jun 13, 2025 | Correspondence Mailed/Faxed/E-mailed |
Jun 13, 2025 | Correspondence Mailed/Faxed/E-mailed |
Jun 17, 2025 | Additional Information Received |
Jun 18, 2025 | Application Accepted |
Jun 18, 2025 | Project Manager |
Jun 18, 2025 | Bio Team Review for Completeness |
Jun 24, 2025 | HPHC Historical Preservation No Effect |
Jul 31, 2025 | Biologist Report |
Aug 04, 2025 | Typist for Processing |
Aug 04, 2025 | Executive Sign Off |
Aug 04, 2025 | Sent to Photo Copy |
Aug 04, 2025 | Permit Approved |
Aug 06, 2025 | Permit Mailed |