Action Date | Action Description |
---|---|
Land Evidence Date | |
Jun 06, 2025 | Assent Application Received |
Jun 06, 2025 | CHA Worksheet received |
Jun 10, 2025 | Administrative Review for Completeness |
Jun 11, 2025 | Bio Team Review for Completeness |
Jun 11, 2025 | Project Manager |
Jun 11, 2025 | Application Accepted |
Jun 24, 2025 | HPHC Historical Preservation No Effect |
Sep 04, 2025 | Biologist Report |
Sep 05, 2025 | Typist for Processing |
Sep 05, 2025 | Executive Sign Off |
Sep 05, 2025 | Sent to Photo Copy |
Sep 05, 2025 | Permit Approved |
Sep 05, 2025 | Dock Post-Construction Certification by Engineer Required. |