| Action Date | Action Description |
|---|---|
| HPHC Review Pending | |
| Engineering Report | |
| Jan 14, 2025 | Maintenance Certification Request |
| Jan 22, 2025 | Administrative Review for Completeness |
| Feb 04, 2025 | Eng Team Review for Completeness |
| Feb 04, 2025 | Deficient Application - Owner Notification Sent |
| May 05, 2025 | Correspondence Received |
| Aug 07, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Aug 20, 2025 | Deficiency Response Received |
| Sep 03, 2025 | Eng Team Review for Completeness |
| Sep 03, 2025 | Application Accepted |
| Sep 03, 2025 | Project Manager |