| Action Date | Action Description |
|---|---|
| May 06, 2007 | HPHC Historical Preservation No Effect |
| Mar 19, 2008 | Assent Application Received |
| Mar 19, 2008 | Administrative Review for Completeness |
| Mar 24, 2008 | Team Review for Completeness |
| Mar 24, 2008 | Application Accepted |
| May 08, 2008 | Biologist Report |
| May 08, 2008 | Typist for Processing |
| May 08, 2008 | Executive Sign Off |
| May 08, 2008 | Sent to Photo Copy |
| May 08, 2008 | Permit Approved |
| May 30, 2008 | Land Evidence Date |
| Jun 17, 2009 | Modification Request |
| Jun 25, 2009 | Administrative Review for Completeness |
| Jun 25, 2009 | Team Review for Completeness |
| Jul 20, 2009 | HPHC Historical Preservation No Effect |
| Aug 03, 2009 | Typist for Processing |
| Aug 03, 2009 | Executive Sign Off |
| Aug 03, 2009 | Sent to Photo Copy |
| Aug 03, 2009 | Modification Approved |
| Aug 03, 2009 | Biologist Report |
| Aug 17, 2009 | Commencement of Work Notice received |
| Aug 25, 2009 | Land Evidence Date |