| Action Date | Action Description |
|---|---|
| Apr 17, 2008 | Assent Application Received |
| Apr 18, 2008 | Administrative Review for Completeness |
| Apr 23, 2008 | Team Review for Completeness |
| Apr 23, 2008 | Team Review for Completeness |
| Apr 23, 2008 | Application Accepted |
| Apr 23, 2008 | Category B assigned |
| Apr 30, 2008 | Joint Public Notice |
| May 01, 2008 | HPHC Historical Preservation No Effect |
| Jun 30, 2008 | Public Notice End Date |
| Jul 01, 2008 | Correspondence Received |
| Feb 07, 2011 | Biologist Report |
| Feb 09, 2011 | Engineering Report |
| Feb 10, 2011 | Executive Signoff of Staff Reports |
| Feb 10, 2011 | Scheduled for Section 110 Review meeting |
| Feb 22, 2011 | Typist for Processing |
| Feb 22, 2011 | Permit Approved |
| Feb 23, 2011 | Executive Sign Off |
| Feb 23, 2011 | Sent to Photo Copy |
| Mar 03, 2011 | Land Evidence Date |
| Mar 11, 2011 | US Army Corps of Engineers Approval Received |