| Action Date | Action Description |
|---|---|
| Jan 15, 2013 | Assent Application Received |
| Jan 16, 2013 | Administrative Review for Completeness |
| Jan 31, 2013 | Additional Information Received |
| Feb 01, 2013 | Application Accepted |
| Feb 01, 2013 | Team Review for Completeness |
| Feb 01, 2013 | Team Review for Completeness |
| Feb 14, 2013 | HPHC Historical Preservation No Effect |
| Mar 14, 2013 | Biologist Report |
| Mar 14, 2013 | Engineering Report |
| Mar 14, 2013 | Additional Information Received |
| Mar 15, 2013 | Typist for Processing |
| Mar 15, 2013 | Executive Sign Off |
| Mar 15, 2013 | Sent to Photo Copy |
| Mar 15, 2013 | Permit Approved |
| May 01, 2013 | Land Evidence Date |
| Sep 08, 2014 | Plans Received |