| Action Date | Action Description |
|---|---|
| Oct 28, 2014 | Assent Application Received |
| Oct 28, 2014 | Administrative Review for Completeness |
| Oct 29, 2014 | Team Review for Completeness |
| Oct 29, 2014 | Team Review for Completeness |
| Oct 29, 2014 | Application Accepted |
| Nov 07, 2014 | HPHC Historical Preservation No Effect |
| Nov 07, 2014 | 30 day Public Notice Issued |
| Dec 01, 2014 | Withdrawal Request Received |
| Dec 07, 2014 | Public Notice End Date |
| Jan 02, 2015 | Objections/Comments Received |
| Jan 06, 2015 | US Army Corps of Engineers Approval Received |
| Feb 10, 2015 | Correspondence Received |
| Feb 17, 2015 | Objections/Comments Received |
| Feb 18, 2015 | Dock Meeting -- Approval |
| Feb 26, 2015 | Plans Received |
| Apr 17, 2015 | Objection withdrawal received |
| Apr 22, 2015 | Biologist Report |
| Apr 22, 2015 | Engineering Report |
| Apr 23, 2015 | Typist for Processing |
| Apr 23, 2015 | Executive Sign Off |
| Apr 23, 2015 | Sent to Photo Copy |
| Jun 29, 2015 | Land Evidence Date |