| Action Date | Action Description |
|---|---|
| Feb 28, 2017 | Assent Application Received |
| Feb 28, 2017 | Administrative Review for Completeness |
| Mar 01, 2017 | Team Review for Completeness |
| Mar 01, 2017 | Application Accepted |
| Mar 06, 2017 | Additional Information Requested from Applicant |
| Mar 24, 2017 | Plans Received |
| Apr 05, 2017 | HPHC Historical Preservation No Effect |
| Apr 07, 2017 | Biologist Report |
| Apr 11, 2017 | Typist for Processing |
| Apr 11, 2017 | Executive Sign Off |
| Apr 11, 2017 | Sent to Photo Copy |
| Apr 11, 2017 | Permit Approved |
| May 08, 2017 | Land Evidence Date |