| Action Date | Action Description |
|---|---|
| Oct 17, 2017 | Assent Application Received |
| Oct 18, 2017 | Administrative Review for Completeness |
| Oct 19, 2017 | Team Review for Completeness |
| Oct 19, 2017 | Application Accepted |
| Oct 20, 2017 | Category B assigned |
| Oct 30, 2017 | HPHC Historical Preservation No Effect |
| Nov 03, 2017 | 30 day Public Notice Issued |
| Nov 30, 2017 | Dock Meeting -- Approval |
| Dec 03, 2017 | Public Notice End Date |
| Dec 20, 2017 | Plans Received |
| Dec 20, 2017 | Biologist Report |
| Dec 21, 2017 | Typist for Processing |
| Dec 21, 2017 | Executive Sign Off |
| Dec 21, 2017 | Sent to Photo Copy |
| Dec 21, 2017 | Permit Approved |
| Jan 02, 2018 | US Army Corps of Engineers Approval Received |
| Jan 12, 2018 | Land Evidence Date |
| Nov 07, 2018 | Dock Post-Construction Certification by Engineer received. |