| Action Date | Action Description |
|---|---|
| Feb 28, 2022 | Assent Application Received |
| Mar 03, 2022 | Administrative Review for Completeness |
| Mar 21, 2022 | Eng Team Review for Completeness |
| Mar 21, 2022 | Deficient Application - Owner Notification Sent |
| May 11, 2023 | Deficiency Response Received |
| May 26, 2023 | Eng Team Review for Completeness |
| May 26, 2023 | Application Accepted |
| May 26, 2023 | Project Manager |
| Jul 03, 2023 | HPHC Historical Preservation No Effect |
| Oct 24, 2023 | Engineering Report |
| Oct 27, 2023 | Typist for Processing |
| Oct 27, 2023 | Executive Sign Off |
| Oct 27, 2023 | Sent to Photo Copy |
| Oct 27, 2023 | Permit Approved |
| Oct 31, 2023 | Permit Mailed |
| Dec 07, 2023 | Land Evidence Date |