| Action Date | Action Description |
|---|---|
| Apr 11, 2022 | Assent Application Received |
| Apr 15, 2022 | Administrative Review for Completeness |
| Apr 20, 2022 | Bio Team Review for Completeness |
| Apr 20, 2022 | Deficient Application - Owner Notification Sent |
| Apr 27, 2022 | Phone Call |
| May 02, 2022 | Deficient Application Picked Up |
| Jun 03, 2022 | Deficiency Response Received |
| Jun 10, 2022 | Bio Team Review for Completeness |
| Jun 10, 2022 | Application Accepted |
| Jun 13, 2022 | Project Manager |
| Jul 07, 2022 | HPHC Historical Preservation No Effect |
| Jul 07, 2022 | HPHC Review Pending |
| Jul 11, 2022 | Biologist Report |
| Jul 21, 2022 | Typist for Processing |
| Jul 21, 2022 | Permit Approved |
| Jul 25, 2022 | Permit Mailed |
| Aug 05, 2022 | Land Evidence Date |