| Action Date | Action Description |
|---|---|
| Jan 06, 2005 | Assent Application Received |
| Jan 06, 2005 | Administrative Review for Completeness |
| Jan 10, 2005 | Team Review for Completeness |
| Jan 10, 2005 | Category B assigned |
| Jan 10, 2005 | Application Accepted |
| Jan 20, 2005 | 30 day Public Notice Issued |
| Jan 28, 2005 | HPHC Review Pending |
| Feb 20, 2005 | Public Notice End Date |
| Feb 24, 2005 | Supervisor Engineer SignOff |
| Feb 24, 2005 | Supervisor Biologist SignOff |
| Feb 24, 2005 | Management Review |
| Feb 24, 2005 | Engineering Report |
| Feb 24, 2005 | Biologist Report |
| Mar 01, 2005 | Ready to Schedule Semi-Monthly Meeting |
| Mar 01, 2005 | Semi-Monthly Meeting Date Scheduled |
| Mar 01, 2005 | Mail Agenda Notice |
| Mar 08, 2005 | Semi-Monthly Meeting Held |
| Mar 08, 2005 | Council Approval Granted |
| Mar 11, 2005 | Water Quality Certification |
| Mar 28, 2005 | Stipulation Package from Biologist |
| Mar 28, 2005 | Stipulation Package by Engineer |
| Mar 28, 2005 | Typist for Processing |
| Mar 28, 2005 | Executive Sign Off |
| Mar 28, 2005 | Sent to Photo Copy |
| Mar 28, 2005 | Permit Approved |
| Apr 04, 2005 | Land Evidence Date |
| Apr 05, 2005 | Executive Sign Off |
| Apr 05, 2005 | Legal Response/Decision |