| Action Date | Action Description |
|---|---|
| May 26, 2005 | Assent Application Received |
| May 27, 2005 | Administrative Review for Completeness |
| Jun 13, 2005 | Team Review for Completeness |
| Jun 13, 2005 | Application Accepted |
| Sep 27, 2005 | Biologist Report |
| Dec 23, 2005 | Supervisor Biologist SignOff |
| Dec 23, 2005 | Plans Received |
| Feb 07, 2006 | Plans Received |
| Feb 27, 2006 | Executive Sign Off |
| Feb 28, 2006 | Typist for Processing |
| Feb 28, 2006 | Executive Sign Off |
| Feb 28, 2006 | Sent to Photo Copy |
| Feb 28, 2006 | Permit Approved |
| Mar 03, 2006 | Land Evidence Date |
| Apr 17, 2006 | Modification Request |
| Apr 18, 2006 | Administrative Review for Completeness |
| Apr 20, 2006 | Team Review for Completeness |
| May 17, 2006 | Biologist Report |
| May 17, 2006 | Typist for Processing |
| May 17, 2006 | Executive Sign Off |
| May 17, 2006 | Sent to Photo Copy |
| May 17, 2006 | Modification Approved |
| May 22, 2006 | Land Evidence Date |