| Action Date | Action Description |
|---|---|
| Jul 01, 2010 | Assent Application Received |
| Jul 02, 2010 | Administrative Review for Completeness |
| Jul 02, 2010 | Team Review for Completeness |
| Jul 06, 2010 | Team Review for Completeness |
| Jul 21, 2010 | Deficient Application - Owner Notification Sent |
| Jul 30, 2010 | Deficiency Response Received |
| Jul 30, 2010 | Team Review for Completeness |
| Jul 30, 2010 | Team Review for Completeness |
| Jul 30, 2010 | Application Accepted |
| Aug 12, 2010 | HPHC Historical Preservation No Effect |
| Sep 08, 2010 | Biologist Report |
| Sep 08, 2010 | Engineering Report |
| Sep 13, 2010 | Typist for Processing |
| Sep 13, 2010 | Permit Approved |
| Sep 15, 2010 | Executive Sign Off |
| Sep 15, 2010 | Sent to Photo Copy |
| Oct 01, 2010 | Land Evidence Date |