| Action Date | Action Description |
|---|---|
| Aug 07, 2013 | Assent Application Received |
| Aug 08, 2013 | Administrative Review for Completeness |
| Aug 08, 2013 | Team Review for Completeness |
| Aug 27, 2013 | Deficient Application - Owner Notification Sent |
| Sep 05, 2013 | Deficiency Response Received |
| Sep 12, 2013 | Team Review for Completeness |
| Sep 12, 2013 | Application Accepted |
| Sep 26, 2013 | HPHC Historical Preservation No Effect |
| Sep 30, 2013 | 30 day Public Notice Issued |
| Oct 30, 2013 | Public Notice End Date |
| Nov 01, 2013 | Public Notice End Date Extension Granted |
| Nov 12, 2013 | Correspondence Received |
| Jan 31, 2014 | US Army Corps of Engineers Approval Received |
| May 07, 2014 | Biologist Report |
| May 15, 2014 | Typist for Processing |
| May 15, 2014 | Permit Approved |
| May 20, 2014 | Executive Sign Off |
| May 20, 2014 | Sent to Photo Copy |
| Jun 04, 2014 | Land Evidence Date |
| Jul 14, 2014 | Correspondence Received |