| Action Date | Action Description |
|---|---|
| Jul 17, 2017 | Maintenance Certification Request |
| Jul 18, 2017 | Administrative Review for Completeness |
| Sep 14, 2018 | Team Review for Completeness |
| Sep 14, 2018 | Application Accepted |
| Oct 02, 2018 | HPHC Historical Preservation No Effect |
| Nov 01, 2019 | Biologist Report |
| Nov 01, 2019 | Typist for Processing |
| Nov 01, 2019 | Executive Sign Off |
| Nov 01, 2019 | Sent to Photo Copy |
| Nov 01, 2019 | Permit Approved |
| Oct 24, 2022 | Extension of Permit Request |
| Mar 24, 2023 | Enforcement Compliance Inspection Required |
| Mar 28, 2023 | Process Extension |
| Mar 28, 2023 | Extension Approved |