| Action Date | Action Description |
|---|---|
| Sep 01, 2017 | Assent Application Received |
| Sep 05, 2017 | Administrative Review for Completeness |
| Sep 12, 2017 | Team Review for Completeness |
| Sep 18, 2017 | Deficient Application - Owner Notification Sent |
| Nov 15, 2017 | Assent Application Received |
| Nov 15, 2017 | Administrative Review for Completeness |
| Nov 27, 2017 | Team Review for Completeness |
| Nov 27, 2017 | Application Accepted |
| Nov 27, 2017 | Team Review for Completeness |
| Dec 05, 2017 | HPHC Historical Preservation No Effect |
| Dec 15, 2017 | Biologist Report |
| Dec 15, 2017 | Engineering Report |
| Dec 18, 2017 | Typist for Processing |
| Dec 18, 2017 | Executive Sign Off |
| Dec 18, 2017 | Sent to Photo Copy |
| Dec 18, 2017 | Permit Approved |
| Jan 17, 2018 | Land Evidence Date |