| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 16, 2020 | Assent Application Received |
| Nov 18, 2020 | Administrative Review for Completeness |
| Nov 30, 2020 | Additional Information Requested from Applicant |
| Dec 09, 2020 | Application Accepted |
| Dec 09, 2020 | Project Manager |
| Dec 09, 2020 | CHA Worksheet received |
| Dec 09, 2020 | Bio Team Review for Completeness |
| Jan 15, 2021 | HPHC Review Pending |
| Jan 15, 2021 | HPHC Historical Preservation No Effect |
| Jan 20, 2021 | Additional Information Requested from Applicant |
| Jan 22, 2021 | Plans Received |
| Jan 22, 2021 | Stipulation Package from Biologist |
| Jan 22, 2021 | Typist for Processing |
| Jan 22, 2021 | Executive Sign Off |
| Jan 22, 2021 | Sent to Photo Copy |
| Jan 22, 2021 | Permit Approved |
| Jan 22, 2021 | Biologist Report |
| Jan 28, 2021 | Land Evidence Date |