| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Sep 21, 2023 | Freshwater Wetlands Application - New - received |
| Sep 25, 2023 | Administrative Review for Completeness |
| Apr 18, 2024 | Phone Call |
| Jun 06, 2024 | Additional Information Received |
| Jun 06, 2024 | Additional Information Requested from Applicant |
| Jun 07, 2024 | Correspondence Received |
| Jul 11, 2024 | Additional Information Received |
| Jul 12, 2024 | Application Accepted |
| Jul 12, 2024 | Category A assigned |
| Jul 12, 2024 | Bio Team Review for Completeness |
| Jul 12, 2024 | Project Manager |
| Jul 15, 2024 | Additional Information Received |
| Aug 08, 2024 | HPHC Historical Preservation No Effect |
| Aug 27, 2024 | Permit Approved |