| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Oct 31, 2023 | Assent Application Received |
| Nov 03, 2023 | Administrative Review for Completeness |
| Nov 07, 2023 | Bio Team Review for Completeness |
| Nov 07, 2023 | Application Accepted |
| Nov 07, 2023 | Project Manager |
| Nov 24, 2023 | HPHC Historical Preservation No Effect |
| Dec 18, 2023 | 30 day Public Notice Issued |
| Jan 18, 2024 | Public Notice End Date |
| Feb 09, 2024 | Dock/1.1.6 Review approval |
| Feb 14, 2024 | Biologist Report |
| Feb 16, 2024 | Typist for Processing |
| Feb 16, 2024 | Executive Sign Off |
| Feb 16, 2024 | Sent to Photo Copy |
| Feb 16, 2024 | Permit Approved |
| Feb 20, 2024 | Permit Mailed |
| Feb 26, 2024 | Land Evidence Date |