| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Dec 16, 1994 | Application Accepted |
| Apr 05, 1995 | Engineering Report |
| Apr 06, 1995 | Permit Approved |
| Apr 06, 1995 | Land Evidence Date |
| Nov 20, 2018 | Modification Request |
| Nov 20, 2018 | Administrative Review for Completeness |
| Nov 26, 2018 | Team Review for Completeness |
| Dec 21, 2018 | Deficient Application - Owner Notification Sent |
| Jan 24, 2019 | Deficiency Response Received |
| Jan 28, 2019 | Team Review for Completeness |
| Jan 28, 2019 | Application Accepted |
| Feb 20, 2019 | HPHC Historical Preservation No Effect |
| Feb 25, 2019 | 30 day Public Notice Issued |
| Mar 25, 2019 | Public Notice End Date |
| Apr 05, 2019 | Dock/1.1.6 Review approval |
| Apr 10, 2019 | Engineering Report |
| Apr 11, 2019 | Typist for Processing |
| Apr 11, 2019 | Executive Sign Off |
| Apr 11, 2019 | Sent to Photo Copy |
| Apr 11, 2019 | Permit Approved |
| May 10, 2019 | Land Evidence Date |