| Action Date | Action Description |
|---|---|
| Sep 30, 2002 | Application Accepted |
| Oct 31, 2002 | Engineering Report |
| Nov 13, 2002 | Permit Approved |
| Nov 13, 2002 | Land Evidence Date |
| Apr 08, 2019 | Correspondence Mailed/Faxed/E-mailed |
| Apr 22, 2019 | Modification Request |
| Apr 24, 2019 | Administrative Review for Completeness |
| Apr 24, 2019 | Team Review for Completeness |
| Apr 24, 2019 | Application Accepted |
| Apr 25, 2019 | Category A* (Docks) |
| May 08, 2019 | Biologist Report |
| May 09, 2019 | Modification Approved |
| May 10, 2019 | HPHC Historical Preservation No Effect |
| May 10, 2019 | HPHC Review Pending |
| Jun 17, 2019 | Assent Requirement |
| Nov 30, 2020 | Modification Request |
| Dec 01, 2020 | Administrative Review for Completeness |
| Dec 03, 2020 | Bio Team Review for Completeness |
| Dec 04, 2020 | Application Accepted |
| Dec 23, 2020 | HPHC Historical Preservation No Effect |
| Dec 23, 2020 | HPHC Review Pending |
| Dec 28, 2020 | 30 day Public Notice Issued |
| Jan 28, 2021 | Public Notice End Date |
| Feb 22, 2021 | Plans Received |
| Feb 26, 2021 | Additional Information Received |
| Mar 01, 2021 | Additional Information Received |
| Mar 04, 2021 | 30 day Public Notice Issued |
| Mar 08, 2021 | Additional Information Received |
| Apr 01, 2021 | Entry of Appearance Received |
| Apr 04, 2021 | Public Notice End Date |
| May 18, 2021 | Plans Received |
| May 25, 2021 | 30 day Public Notice Issued |
| Jun 24, 2021 | Objections/Comments Received |
| Jun 24, 2021 | Entry of Appearance Received |
| Jun 25, 2021 | Public Notice End Date |
| Jul 23, 2021 | Additional Information Received |
| Aug 03, 2021 | Additional Information Received |
| Sep 14, 2021 | Additional Information Received |
| Nov 08, 2021 | Objections/Comments Received |
| Aug 15, 2022 | Additional Information Received |
| Oct 17, 2022 | 30-Day Notification of Cancellation letter |
| Nov 09, 2022 | Plans Received |
| Nov 22, 2022 | 30 day Public Notice Issued |
| Nov 25, 2022 | Additional Information Received |
| Dec 09, 2022 | Objections/Comments Received |
| Dec 12, 2022 | Objections/Comments Received |
| Dec 22, 2022 | Public Notice End Date |
| Dec 30, 2022 | Objections/Comments Received |
| Jan 31, 2023 | Additional Information Received |
| Feb 06, 2023 | Plans Received |
| Feb 13, 2023 | Additional Information Received |
| Mar 16, 2023 | Additional Information Received |
| Jun 08, 2023 | Objection withdrawal received |
| Aug 01, 2023 | Dock/1.1.6 Review approval |
| Sep 13, 2023 | Biologist Report |
| Sep 19, 2023 | Typist for Processing |
| Sep 19, 2023 | Executive Sign Off |
| Sep 19, 2023 | Sent to Photo Copy |
| Sep 19, 2023 | Modification Approved |
| Sep 20, 2023 | Permit Mailed |
| Oct 23, 2023 | Land Evidence Date |
| Sep 24, 2024 | Dock Plate re-issue |