| Action Date | Action Description |
|---|---|
| Process Extension | |
| Feb 10, 2003 | Conservation Easement Recording received |
| Aug 20, 2003 | Application Accepted |
| Aug 20, 2003 | 30 day Public Notice Issued |
| Aug 20, 2003 | Category B assigned |
| Aug 21, 2003 | ISDS Approved |
| Aug 28, 2003 | Historical Preservation Approval Granted |
| Sep 04, 2003 | Biologist Report |
| Sep 12, 2003 | Engineering Report |
| Sep 23, 2003 | Meeting Held |
| Oct 02, 2003 | Council Approval Granted |
| Dec 04, 2003 | Water Quality Certification |
| Jan 26, 2004 | Permit Approved |
| Jan 26, 2004 | Land Evidence Date |
| May 29, 2004 | Modification Request |
| Jun 01, 2004 | Engineering Report |
| Jun 01, 2004 | Typist for Processing |
| Jun 07, 2004 | Modification Approved |
| Jan 03, 2006 | Correspondence Received |
| Feb 06, 2006 | Water Quality Certification |
| Nov 16, 2006 | Correspondence Received |
| Jan 19, 2007 | Extension of Permit Request |
| Mar 05, 2007 | Enforcement Compliance Inspection Required |
| Mar 05, 2007 | Process Extension |
| Mar 05, 2007 | Extension Approved |
| Jan 08, 2008 | Extension of Permit Request |
| Apr 15, 2008 | Enforcement Compliance Inspection Required |
| Apr 16, 2008 | Process Extension |
| Apr 16, 2008 | Executive Sign Off |
| Apr 16, 2008 | Extension Approved |
| Dec 04, 2008 | Modification Request |
| Dec 05, 2008 | Administrative Review for Completeness |
| Dec 05, 2008 | Extension of Permit Request |
| Dec 05, 2008 | Enforcement Compliance Inspection Required |
| Dec 09, 2008 | Team Review for Completeness |
| Dec 09, 2008 | Team Review for Completeness |
| Dec 15, 2008 | Biologist Report |
| Dec 15, 2008 | Engineering Report |
| Dec 18, 2008 | Typist for Processing |
| Dec 18, 2008 | Executive Sign Off |
| Dec 18, 2008 | Sent to Photo Copy |
| Dec 18, 2008 | Modification Approved |
| Dec 22, 2008 | HPHC Historical Preservation No Effect |
| Feb 12, 2009 | Land Evidence Date |