| Action Date | Action Description |
|---|---|
| Sep 20, 2004 | Application Accepted |
| Sep 22, 2004 | Engineering Report |
| Sep 28, 2004 | 30 day Public Notice Issued |
| Sep 28, 2004 | Meeting Held |
| Oct 05, 2004 | Historical Preservation Approval Granted |
| Oct 13, 2004 | Permit Approved |
| Oct 13, 2004 | Land Evidence Date |
| May 16, 2005 | Engineering Report |
| May 19, 2005 | Executive Sign Off |
| May 19, 2005 | Legal Response/Decision |
| Apr 16, 2007 | Correspondence Received |
| Apr 23, 2007 | Correspondence Mailed/Faxed/E-mailed |
| Apr 27, 2007 | Extension of Permit Request |
| Aug 16, 2007 | Enforcement Compliance Inspection Required |
| Aug 21, 2007 | Process Extension |
| Aug 21, 2007 | Typist for Processing |
| Aug 21, 2007 | Executive Sign Off |
| Aug 21, 2007 | Sent to Photo Copy |
| Aug 21, 2007 | Extension Approved |
| Aug 27, 2007 | Land Evidence Date |
| Jun 30, 2008 | Extension of Permit Request |
| Sep 08, 2008 | Enforcement Compliance Inspection Required |
| Sep 09, 2008 | Process Extension |
| Sep 09, 2008 | Extension Approved |
| Jul 29, 2009 | Extension of Permit Request |
| Sep 11, 2009 | Enforcement Compliance Inspection Required |
| Sep 11, 2009 | Process Extension |
| Sep 11, 2009 | Extension Approved |
| Sep 20, 2010 | Extension of Permit Request |
| Feb 25, 2011 | Extension Toll letter mailed |