| Action Date | Action Description |
|---|---|
| Feb 22, 2005 | Assent Application Received |
| Feb 23, 2005 | Administrative Review for Completeness |
| Feb 28, 2005 | Team Review for Completeness |
| Feb 28, 2005 | Application Accepted |
| Feb 28, 2005 | Engineering Report |
| Mar 07, 2005 | Typist for Processing |
| Mar 07, 2005 | Executive Sign Off |
| Mar 07, 2005 | Sent to Photo Copy |
| Mar 08, 2005 | Permit Approved |
| Mar 18, 2005 | Land Evidence Date |