| Action Date | Action Description |
|---|---|
| Mar 10, 2005 | Maintenance Certification Request |
| Mar 11, 2005 | Administrative Review for Completeness |
| Mar 22, 2005 | Team Review for Completeness |
| Mar 22, 2005 | Application Accepted |
| Mar 30, 2005 | Biologist Report |
| Mar 30, 2005 | Engineering Report |
| Apr 08, 2005 | Typist for Processing |
| Apr 08, 2005 | Executive Sign Off |
| Apr 08, 2005 | Sent to Photo Copy |
| Apr 08, 2005 | Permit Approved |
| Apr 15, 2005 | Historical Preservation Approval Granted |