| Action Date | Action Description |
|---|---|
| Mar 14, 2005 | Assent Application Received |
| Mar 15, 2005 | Administrative Review for Completeness |
| Mar 18, 2005 | Team Review for Completeness |
| Mar 18, 2005 | Application Accepted |
| Mar 21, 2005 | Plans Received |
| Apr 01, 2005 | Historical Preservation Approval Granted |
| Apr 01, 2005 | HPHC Review Pending |
| Apr 06, 2005 | Engineering Report |
| Apr 08, 2005 | Typist for Processing |
| Apr 08, 2005 | Executive Sign Off |
| Apr 08, 2005 | Sent to Photo Copy |
| Apr 08, 2005 | Permit Approved |