| Action Date | Action Description |
|---|---|
| Mar 21, 2005 | Assent Application Received |
| Mar 24, 2005 | Administrative Review for Completeness |
| Mar 30, 2005 | Deficient Application - Owner Notification Sent |
| Apr 05, 2005 | Deficient Application Picked Up |
| Apr 13, 2005 | Deficiency Response Received |
| Apr 14, 2005 | Team Review for Completeness |
| Apr 14, 2005 | Application Accepted |
| May 03, 2005 | HPHC Review Pending |
| Jun 09, 2005 | Biologist Report |
| Jun 09, 2005 | Engineering Report |
| Jun 09, 2005 | Typist for Processing |
| Jun 09, 2005 | Executive Sign Off |
| Jun 09, 2005 | Sent to Photo Copy |
| Jun 09, 2005 | Permit Approved |
| Jun 24, 2005 | Land Evidence Date |