| Action Date | Action Description |
|---|---|
| May 23, 2005 | Assent Application Received |
| May 23, 2005 | Administrative Review for Completeness |
| Jun 28, 2005 | Team Review for Completeness |
| Jun 28, 2005 | Application Accepted |
| Jul 14, 2005 | HPHC Review Pending |
| Nov 10, 2005 | Additional Information Received |
| Nov 14, 2005 | 30 day Public Notice Issued |
| Dec 12, 2005 | Engineering Report |
| Dec 13, 2005 | Biologist Report |
| Dec 13, 2005 | Supervisor Biologist SignOff |
| Dec 13, 2005 | Executive Sign Off |
| Dec 14, 2005 | Public Notice End Date |
| Dec 29, 2005 | US Army Corp of Engineers Permit Date |
| Jan 03, 2006 | US Army Corps of Engineers Approval Received |
| Feb 23, 2006 | Mail Agenda Notice |
| Feb 23, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Mar 14, 2006 | Semi-Monthly Meeting Date Scheduled |
| Mar 21, 2006 | Mail Agenda Notice |
| Mar 28, 2006 | Semi-Monthly Meeting Held |
| Mar 28, 2006 | Council Approval Granted |
| Mar 28, 2006 | Semi-Monthly Meeting Date Scheduled |
| Apr 12, 2006 | Stipulation Package from Biologist |
| Apr 12, 2006 | Stipulation Package by Engineer |
| Apr 12, 2006 | Legal Response/Decision |
| Apr 12, 2006 | Typist for Processing |
| Apr 12, 2006 | Executive Sign Off |
| Apr 12, 2006 | Sent to Photo Copy |
| Apr 12, 2006 | Permit Approved |
| Apr 18, 2006 | Land Evidence Date |