| Action Date | Action Description |
|---|---|
| Aug 24, 2005 | Assent Application Received |
| Aug 25, 2005 | Administrative Review for Completeness |
| Sep 26, 2005 | Team Review for Completeness |
| Sep 26, 2005 | Application Accepted |
| Sep 26, 2005 | Category A* (Docks) |
| Oct 05, 2005 | Historical Preservation Approval Granted |
| Oct 05, 2005 | HPHC Review Pending |
| Oct 12, 2005 | 30 day Public Notice Issued |
| Nov 12, 2005 | Public Notice End Date |
| Nov 16, 2005 | US Army Corp of Engineers Permit Date |
| Nov 21, 2005 | US Army Corps of Engineers Approval Received |
| Nov 22, 2005 | Correspondence Received |
| Nov 22, 2005 | Biologist Report |
| Dec 02, 2005 | Entry of Appearance Received |
| Jan 25, 2006 | Plans Received |
| Mar 02, 2006 | Engineering Report |
| Mar 10, 2006 | Supervisor Biologist SignOff |
| Mar 10, 2006 | Supervisor Engineer SignOff |
| Mar 10, 2006 | Executive Sign Off |
| Mar 30, 2006 | Mail Agenda Notice |
| Apr 11, 2006 | Semi-Monthly Meeting Held |
| Apr 11, 2006 | Council Approval Granted |
| Apr 11, 2006 | Semi-Monthly Meeting Date Scheduled |
| Apr 18, 2006 | Correspondence Received |
| Apr 18, 2006 | Stipulation Package by Engineer |
| Apr 20, 2006 | Correspondence Received |
| Apr 24, 2006 | Legal Response/Decision |
| May 05, 2006 | Correspondence Mailed/Faxed/E-mailed |
| May 05, 2006 | 30 Day Appeal Notification to Owner |
| May 05, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Jun 08, 2006 | Correspondence Received |
| Jun 14, 2006 | Typist for Processing |
| Jun 14, 2006 | Executive Sign Off |
| Jun 14, 2006 | Sent to Photo Copy |
| Jun 14, 2006 | Permit Approved |
| Jun 21, 2006 | Land Evidence Date |