| Action Date | Action Description |
|---|---|
| Sep 09, 2005 | Assent Application Received |
| Sep 12, 2005 | Administrative Review for Completeness |
| Sep 19, 2005 | Team Review for Completeness |
| Sep 19, 2005 | Application Accepted |
| Sep 23, 2005 | Engineering Report |
| Sep 26, 2005 | Typist for Processing |
| Sep 26, 2005 | Executive Sign Off |
| Sep 26, 2005 | Sent to Photo Copy |
| Sep 26, 2005 | Permit Approved |
| Sep 30, 2005 | HPHC Review Pending |
| Oct 14, 2005 | Land Evidence Date |