| Action Date | Action Description |
|---|---|
| Jan 29, 2008 | Assent Application Received |
| Jan 30, 2008 | Administrative Review for Completeness |
| Jan 30, 2008 | Team Review for Completeness |
| Jan 30, 2008 | Team Review for Completeness |
| Jan 30, 2008 | Application Accepted |
| Feb 04, 2008 | Biologist Report |
| Feb 04, 2008 | Engineering Report |
| Feb 05, 2008 | Typist for Processing |
| Feb 05, 2008 | Executive Sign Off |
| Feb 05, 2008 | Sent to Photo Copy |
| Feb 05, 2008 | Permit Approved |
| Feb 18, 2008 | HPHC Historical Preservation No Effect |
| Feb 20, 2008 | Land Evidence Date |
| Aug 22, 2014 | Extension Toll letter mailed |
| Aug 18, 2015 | Extension Toll letter mailed |
| Apr 12, 2017 | Modification Request |
| Apr 14, 2017 | Administrative Review for Completeness |
| Apr 17, 2017 | Team Review for Completeness |
| Apr 17, 2017 | Application Accepted |
| May 08, 2017 | HPHC Historical Preservation No Effect |
| May 24, 2017 | Biologist Report |
| May 31, 2017 | Modification Approved |
| Aug 18, 2017 | Land Evidence Date |