| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| Apr 07, 2008 | Assent Application Received |
| Apr 08, 2008 | Administrative Review for Completeness |
| Apr 08, 2008 | Team Review for Completeness |
| Apr 08, 2008 | Team Review for Completeness |
| Apr 10, 2008 | Deficient Application - Owner Notification Sent |
| Apr 14, 2008 | Deficient Application Picked Up |
| Jul 01, 2008 | Deficiency Response Received |
| Jul 01, 2008 | Administrative Review for Completeness |
| Jul 08, 2008 | Plans Received |
| Jul 09, 2008 | 30 day Public Notice Issued |
| Jul 09, 2008 | Application Accepted |
| Jul 09, 2008 | Team Review for Completeness |
| Jul 09, 2008 | Team Review for Completeness |
| Jul 09, 2008 | Category A* (Docks) |
| Jul 15, 2008 | HPHC Historical Preservation No Effect |
| Jul 28, 2008 | Objections/Comments Received |
| Aug 09, 2008 | Public Notice End Date |
| Sep 03, 2008 | Biologist Report |
| Sep 03, 2008 | Engineering Report |
| Sep 03, 2008 | Supervisor Biologist SignOff |
| Sep 03, 2008 | Supervisor Engineer SignOff |
| Sep 03, 2008 | Executive Signoff of Staff Reports |
| Sep 03, 2008 | US Army Corp of Engineers Permit Date |
| Sep 08, 2008 | US Army Corps of Engineers Approval Received |
| Sep 15, 2008 | Mail Agenda Notice |
| Sep 15, 2008 | Ready to Schedule Semi-Monthly Meeting |
| Sep 18, 2008 | Correspondence Received |
| Sep 22, 2008 | Continuance request by applicant granted by Director |
| Sep 23, 2008 | Semi-Monthly Meeting Date Scheduled |
| Oct 02, 2008 | Mail Agenda Notice |
| Oct 02, 2008 | Ready to Schedule Semi-Monthly Meeting |
| Oct 14, 2008 | Semi-Monthly Meeting Date Scheduled |
| Nov 07, 2008 | Mail Agenda Notice |
| Nov 25, 2008 | Semi-Monthly Meeting Postponed |
| Nov 25, 2008 | Ready to Schedule Semi-Monthly Meeting |
| Nov 25, 2008 | Semi-Monthly Meeting Date Scheduled |
| Nov 26, 2008 | Mail Agenda Notice |
| Dec 01, 2008 | Entry of Appearance Received |
| Dec 09, 2008 | Semi-Monthly Meeting Postponed |
| Dec 09, 2008 | Semi-Monthly Meeting Date Scheduled |
| Dec 11, 2008 | Ready to Schedule Semi-Monthly Meeting |
| Dec 11, 2008 | Mail Agenda Notice |
| Dec 16, 2008 | Continuance Requested |
| Dec 17, 2008 | Management Review |
| Dec 22, 2008 | Correspondence Received |
| Dec 22, 2008 | Mail Agenda Notice |
| Jan 21, 2009 | Mail Agenda Notice |
| Jan 27, 2009 | Semi-Monthly Meeting Held |
| Jan 27, 2009 | Council Approval Granted |
| Jan 27, 2009 | Semi-Monthly Meeting Date Scheduled |
| Jan 29, 2009 | Stipulation Package from Biologist |
| Jan 29, 2009 | Stipulation Package by Engineer |
| Jan 29, 2009 | Permit Approved |
| Jan 29, 2009 | Typist for Processing |
| Jan 29, 2009 | Executive Sign Off |
| Jan 29, 2009 | Sent to Photo Copy |
| Apr 20, 2009 | Land Evidence Date |