| Action Date | Action Description |
|---|---|
| Jul 09, 2008 | Assent Application Received |
| Jul 10, 2008 | Administrative Review for Completeness |
| Jul 10, 2008 | Team Review for Completeness |
| Jul 10, 2008 | Team Review for Completeness |
| Jul 10, 2008 | Application Accepted |
| Jul 14, 2008 | Category A* (Docks) |
| Jul 21, 2008 | 30 day Public Notice Issued |
| Jul 21, 2008 | HPHC Historical Preservation No Effect |
| Jul 29, 2008 | Plans Received |
| Aug 12, 2008 | Correspondence Received |
| Aug 15, 2008 | Plans Received |
| Aug 21, 2008 | Public Notice End Date |
| Aug 22, 2008 | Additional Information Received |
| Sep 24, 2008 | US Army Corp of Engineers Permit Date |
| Sep 25, 2008 | Biologist Report |
| Sep 25, 2008 | Engineering Report |
| Sep 25, 2008 | Typist for Processing |
| Sep 25, 2008 | Executive Sign Off |
| Sep 25, 2008 | Sent to Photo Copy |
| Sep 25, 2008 | Dock Meeting -- Approval |
| Sep 25, 2008 | Permit Approved |
| Oct 01, 2008 | US Army Corps of Engineers Approval Received |
| Oct 03, 2008 | Land Evidence Date |
| Oct 06, 2008 | Commencement of Work Notice received |