| Action Date | Action Description |
|---|---|
| Aug 18, 2008 | Assent Application Received |
| Aug 19, 2008 | Administrative Review for Completeness |
| Sep 02, 2008 | Team Review for Completeness |
| Sep 02, 2008 | Application Accepted |
| Sep 02, 2008 | Category A* (Docks) |
| Sep 12, 2008 | HPHC Historical Preservation No Effect |
| Dec 03, 2008 | 30 day Public Notice Issued |
| Jan 02, 2009 | Public Notice End Date |
| Feb 13, 2009 | Plans Received |
| Mar 23, 2009 | Dock Meeting -- Approval |
| Mar 23, 2009 | US Army Corp of Engineers Permit Date |
| Mar 23, 2009 | Biologist Report |
| Mar 25, 2009 | US Army Corps of Engineers Approval Received |
| Mar 27, 2009 | Typist for Processing |
| Mar 27, 2009 | Executive Sign Off |
| Mar 27, 2009 | Sent to Photo Copy |
| Mar 27, 2009 | Permit Approved |
| Mar 27, 2009 | Engineering Report |
| Apr 17, 2009 | Land Evidence Date |
| Jul 17, 2009 | Modification Request |
| Jul 22, 2009 | Administrative Review for Completeness |
| Jul 29, 2009 | Team Review for Completeness |
| Jul 29, 2009 | Team Review for Completeness |
| Aug 04, 2009 | Biologist Report |
| Aug 04, 2009 | Engineering Report |
| Aug 06, 2009 | Typist for Processing |
| Aug 06, 2009 | Modification Approved |
| Aug 10, 2009 | Executive Sign Off |
| Aug 11, 2009 | Sent to Photo Copy |
| Aug 27, 2009 | HPHC Historical Preservation No Effect |
| Oct 13, 2009 | Commencement of Work Notice received |