| Action Date | Action Description |
|---|---|
| Nov 05, 2008 | Assent Application Received |
| Nov 06, 2008 | Administrative Review for Completeness |
| Nov 12, 2008 | Team Review for Completeness |
| Nov 12, 2008 | Team Review for Completeness |
| Nov 12, 2008 | Application Accepted |
| Nov 12, 2008 | Category A* (Docks) |
| Nov 17, 2008 | HPHC Historical Preservation No Effect |
| Jan 30, 2009 | Plans Received |
| Feb 26, 2009 | 30 day Public Notice Issued |
| Mar 24, 2009 | Objections/Comments Received |
| Mar 25, 2009 | Objections/Comments Received |
| Mar 28, 2009 | Public Notice End Date |
| Jun 22, 2009 | US Army Corp of Engineers Permit Date |
| Jun 24, 2009 | US Army Corps of Engineers Approval Received |
| Nov 30, 2009 | Biologist Report |
| Nov 30, 2009 | Engineering Report |
| Nov 30, 2009 | Mail Agenda Notice |
| Nov 30, 2009 | Executive Signoff of Staff Reports |
| Dec 08, 2009 | Council Approval Granted |
| Dec 08, 2009 | Semi-Monthly Meeting Date Scheduled |
| Jan 25, 2010 | Legal Response/Decision |
| Jan 28, 2010 | Stipulation Package from Biologist |
| Jan 28, 2010 | Stipulation Package by Engineer |
| Jan 29, 2010 | Typist for Processing |
| Jan 29, 2010 | Executive Sign Off |
| Jan 29, 2010 | Sent to Photo Copy |
| Jan 29, 2010 | Permit Approved |
| May 27, 2010 | Land Evidence Date |