| Action Date | Action Description |
|---|---|
| Feb 24, 2009 | Assent Application Received |
| Feb 26, 2009 | Administrative Review for Completeness |
| Feb 26, 2009 | Team Review for Completeness |
| Feb 26, 2009 | Team Review for Completeness |
| Feb 26, 2009 | Application Accepted |
| Mar 04, 2009 | Biologist Report |
| Mar 04, 2009 | Engineering Report |
| Mar 04, 2009 | Typist for Processing |
| Mar 04, 2009 | Executive Sign Off |
| Mar 04, 2009 | Sent to Photo Copy |
| Mar 04, 2009 | Permit Approved |
| Mar 06, 2009 | Land Evidence Date |