| Action Date | Action Description |
|---|---|
| Mar 02, 2009 | Assent Application Received |
| Mar 04, 2009 | Administrative Review for Completeness |
| Mar 04, 2009 | Team Review for Completeness |
| Mar 04, 2009 | Team Review for Completeness |
| Mar 04, 2009 | Application Accepted |
| Mar 13, 2009 | Correspondence Received |
| Apr 07, 2009 | Plans Received |
| Apr 21, 2009 | HPHC Historical Preservation Comments/Concerns |
| May 05, 2009 | Correspondence Received |
| May 27, 2009 | Additional Information Received |
| Jul 29, 2009 | Correspondence Received |
| Aug 03, 2009 | Plans Received |
| Feb 12, 2010 | Water Quality Certification |
| Mar 05, 2010 | Additional Information Received |
| Mar 22, 2010 | Permit Approved |
| Mar 22, 2010 | Biologist Report |
| Mar 22, 2010 | Engineering Report |
| Mar 24, 2010 | Land Evidence Date |
| Apr 19, 2011 | Correspondence Received |
| Jan 30, 2012 | Additional Information Received |
| Feb 06, 2012 | Correspondence Mailed/Faxed/E-mailed |
| Apr 13, 2012 | Modification Request |
| Apr 16, 2012 | Administrative Review for Completeness |
| Apr 16, 2012 | Team Review for Completeness |
| Apr 16, 2012 | Team Review for Completeness |
| Apr 17, 2012 | Biologist Report |
| Apr 17, 2012 | Engineering Report |
| Apr 19, 2012 | Modification Approved |
| Apr 20, 2012 | Typist for Processing |
| Apr 23, 2012 | Executive Sign Off |
| Apr 23, 2012 | Sent to Photo Copy |
| May 09, 2012 | HPHC Historical Preservation No Effect |
| Aug 06, 2013 | Modification Request |
| Aug 07, 2013 | Administrative Review for Completeness |
| Aug 08, 2013 | Team Review for Completeness |
| Aug 22, 2013 | Additional Information Received |
| Aug 23, 2013 | Biologist Report |
| Aug 28, 2013 | Typist for Processing |
| Aug 28, 2013 | Executive Sign Off |
| Aug 28, 2013 | Sent to Photo Copy |
| Aug 28, 2013 | Modification Approved |
| Oct 18, 2013 | Land Evidence Date |