| Action Date | Action Description |
|---|---|
| Apr 02, 2009 | Assent Application Received |
| Apr 04, 2009 | Administrative Review for Completeness |
| Apr 07, 2009 | Team Review for Completeness |
| Apr 07, 2009 | Team Review for Completeness |
| Apr 07, 2009 | Application Accepted |
| Apr 21, 2009 | HPHC Historical Preservation No Effect |
| May 26, 2009 | 30 day Public Notice Issued |
| Jun 16, 2009 | Phone Call |
| Jun 26, 2009 | Public Notice End Date |
| Jun 30, 2009 | US Army Corp of Engineers Permit Date |
| Jul 02, 2009 | US Army Corps of Engineers Approval Received |
| Sep 17, 2009 | Plans Received |
| Nov 03, 2009 | Typist for Processing |
| Nov 03, 2009 | Executive Sign Off |
| Nov 03, 2009 | Sent to Photo Copy |
| Nov 03, 2009 | Permit Approved |
| Nov 03, 2009 | Biologist Report |
| Nov 03, 2009 | Engineering Report |
| Nov 13, 2009 | Land Evidence Date |
| Mar 30, 2010 | Commencement of Work Notice received |