| Action Date | Action Description |
|---|---|
| Apr 10, 2009 | Assent Application Received |
| Apr 15, 2009 | Administrative Review for Completeness |
| Apr 15, 2009 | Team Review for Completeness |
| Apr 15, 2009 | Application Accepted |
| May 20, 2009 | Engineering Report |
| May 27, 2009 | HPHC Historical Preservation No Effect |
| Jul 09, 2009 | Ready to Schedule Semi-Monthly Meeting |
| Jul 09, 2009 | Mail Agenda Notice |
| Jul 13, 2009 | Council Approval Granted |
| Jul 13, 2009 | Semi-Monthly Meeting Date Scheduled |
| Jul 13, 2009 | Semi-Monthly Meeting Held |
| Jul 15, 2009 | Legal Response/Decision |
| Jul 16, 2009 | Stipulation Package by Engineer |
| Jul 16, 2009 | Typist for Processing |
| Jul 16, 2009 | Executive Sign Off |
| Jul 16, 2009 | Permit Approved |
| Feb 25, 2010 | Modification Request |
| Mar 01, 2010 | Administrative Review for Completeness |
| Mar 04, 2010 | Team Review for Completeness |
| Mar 04, 2010 | Engineering Report |
| Mar 08, 2010 | Typist for Processing |
| Mar 08, 2010 | Executive Sign Off |
| Mar 08, 2010 | Sent to Photo Copy |
| Mar 08, 2010 | Modification Approved |
| Mar 15, 2010 | Land Evidence Date |