| Action Date | Action Description |
|---|---|
| May 07, 2009 | Assent Application Received |
| May 11, 2009 | Administrative Review for Completeness |
| May 11, 2009 | Team Review for Completeness |
| May 11, 2009 | Team Review for Completeness |
| May 13, 2009 | Application Accepted |
| May 27, 2009 | Plans Received |
| Jun 05, 2009 | HPHC Historical Preservation No Effect |
| Jun 10, 2009 | Plans Received |
| Jun 11, 2009 | Engineering Report |
| Jun 12, 2009 | Biologist Report |
| Jun 16, 2009 | Typist for Processing |
| Jun 16, 2009 | Executive Sign Off |
| Jun 16, 2009 | Permit Approved |
| Jun 17, 2009 | Sent to Photo Copy |
| Jun 24, 2009 | Land Evidence Date |