| Action Date | Action Description |
|---|---|
| Sep 11, 2009 | Assent Application Received |
| Sep 11, 2009 | Administrative Review for Completeness |
| Sep 18, 2009 | Team Review for Completeness |
| Sep 18, 2009 | Team Review for Completeness |
| Sep 18, 2009 | Application Accepted |
| Nov 09, 2009 | Public Notice End Date |
| May 27, 2010 | Correspondence Received |
| Jun 18, 2010 | Additional Information Received |
| Aug 18, 2010 | Engineering Report |
| Aug 20, 2010 | Biologist Report |
| Aug 26, 2010 | Executive Signoff of Staff Reports |
| Aug 31, 2010 | Ready to Schedule Semi-Monthly Meeting |
| Sep 01, 2010 | Mail Agenda Notice |
| Sep 28, 2010 | Semi-Monthly Meeting Date Scheduled |
| Oct 06, 2010 | Mail Agenda Notice |
| Oct 12, 2010 | Council Approval Granted |
| Oct 12, 2010 | Semi-Monthly Meeting Held |
| Oct 13, 2010 | Semi-Monthly Meeting Date Scheduled |
| Oct 26, 2010 | Legal Response/Decision |
| Nov 08, 2010 | Water Quality Certification |
| Nov 22, 2010 | Stipulation Package from Biologist |
| Nov 22, 2010 | Stipulation Package by Engineer |
| Dec 02, 2010 | Typist for Processing |
| Dec 02, 2010 | Permit Approved |
| Dec 03, 2010 | Executive Sign Off |
| Dec 03, 2010 | Sent to Photo Copy |
| Jan 05, 2011 | Correspondence Received |
| Jan 13, 2012 | Commencement of Work Notice received |
| Jun 28, 2012 | Site Inspection |