| Action Date | Action Description |
|---|---|
| Jul 07, 2010 | Assent Application Received |
| Jul 09, 2010 | Administrative Review for Completeness |
| Jul 16, 2010 | Team Review for Completeness |
| Jul 16, 2010 | Team Review for Completeness |
| Jul 16, 2010 | Application Accepted |
| Jul 23, 2010 | Engineering Report |
| Jul 23, 2010 | Biologist Report |
| Jul 26, 2010 | HPHC Historical Preservation No Effect |
| Jul 27, 2010 | Typist for Processing |
| Jul 27, 2010 | Executive Sign Off |
| Jul 27, 2010 | Sent to Photo Copy |
| Jul 27, 2010 | Permit Approved |
| Sep 27, 2011 | Modification Request |
| Sep 28, 2011 | Administrative Review for Completeness |
| Sep 28, 2011 | Team Review for Completeness |
| Sep 28, 2011 | Engineering Report |
| Oct 06, 2011 | Typist for Processing |
| Oct 06, 2011 | Modification Approved |
| Oct 11, 2011 | Executive Sign Off |
| Oct 12, 2011 | Sent to Photo Copy |
| Nov 25, 2011 | Modification Request |
| Dec 02, 2011 | Administrative Review for Completeness |
| Dec 02, 2011 | Team Review for Completeness |
| Dec 07, 2011 | Modification Approved |
| Dec 09, 2011 | Typist for Processing |
| Dec 12, 2011 | Executive Sign Off |
| Dec 12, 2011 | Sent to Photo Copy |